DECISION TRACKER

The CIF Decision Tracker is an open access database that compiles all policy decisions taken by the CIF Trust Fund Committees and Sub-Committees during their semi-annual and intersessional meetings. It follows policy decisions through the entire decision-making process, from inception to enactment, to support more efficient work flow and greater transparency and accountability. Whenever possible, the tracker includes the resulting action taken to fulfill the demands of a decision (often a final report document). Users can sort the decisions through a variety of filters to tailor their search for information.

Program Meeting Date Task Reporting Methodology Status Exptected Completed Date Final Document Commentssort icon
SREP 03/01/2019

Provide information on timing and scale of disbursements and cancellation 

Related Decision

Committee Meeting Completed June 2019 Included in the disbursement report
FIP 03/01/2019

To include in FIP SAR: a) explore ways to enhance reporting on overall portfolio progress monitoring; b) explore ways to enhance reporting on overall portfolio progress monitoring; c) identify pathways to further support recipient countries in their investment plan implementation process

Related Decision

Committee Meeting Completed June 2019 Included in the FIP SAR
CTF 03/01/2019

To Include in risk report: a) Detailed information on projects facing implementation risks in relation to the private sector portfolio;b) Information regarding fraud and sexual exploitation and abuse in CTF projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements;c) Report risk trends

Related Decision

Committee Meeting Completed June 2019 Included in the risk report of the CTF
FIP 03/01/2019

To Include in risk report: a) details of the rationales for the implementation delays in projects flagged under implementation risk; b) details of actions taken to address the implementation delays in projects flagged for implementation risk as well as a workplan for ensuring that disbursements under these flagged projects will increase to a level where the projects will no longer be flagged for this risk; c) estimates of the dates by which disbursements will increase to levels such that these projects will no longer be flagged for implementation risk; d) Information regarding fraud and sexual exploitation and abuse in FIP projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements;e) Report risk trends

Related Decision

Committee Meeting Completed June 2019 Included in the risk report of the FIP
SREP 03/01/2019

To Include in risk report: a) details of the rationales for the implementation delays in projects flagged under implementation risk; b) details of actions taken to address the implementation delays in projects flagged for implementation risk as well as a workplan for ensuring that disbursements under these flagged projects will increase to a level where the projects will no longer be flagged for this risk; c) estimates of the dates by which disbursements will increase to levels such that these projects will no longer be flagged for implementation risk; d) Information regarding fraud and sexual exploitation and abuse in FIP projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements; e)Report risk trends

Related Decision

Committee Meeting Completed June 2019 Included in the risk report of the SREP
FIP 05/15/2015

Update in SAR: Status updates for FIP pilot countries that explore the link to performance-based payment mechanisms, including efforts to improve collaboration and coordination at the country-level

Related Decision

Committee Meeting Completed June 2016 Information on updates for FIP pilot countries that are recipients of other REDD+ programs are included in the SAR
CTF 06/06/2017

To develop a proposal for utilizing any resources available by July 1, 2017 for further programming

Related Decision

Intersessional Meeting Completed March 2018 Intersessional Meeting
joint 11/09/2015

Request to launch ERM Dashboards for SCF Sub Program

Related Decision

Ongoing Ongoing December 2016 It is an ongoing process
CTF 11/10/2015

Explore currency risk mitigation strategies associated with unencashed promissory notes

Related Decision

Committee Meeting Completed June 2016 It was mentioned during the June 2016 Trust Fund committee meeting that this option is not feasible
PPCR 11/18/2014

Share lessons from PPCR Phase 1 for Enhancing Readiness for Climate-Resilient Development with interested stakeholders

Related Decision

Ongoing Ongoing On going process
joint 12/15/2017

To include a summary of risk exposure assessments related to the funding programs that is currently being included in the joint Risk Reports of the CTF and the SCF in the next CTF,SREP,FIP and PPCR operational and results reports.

Related Decision

Committee Meeting Completed June 2018 Part of SAR. Please refer to each of the TFC/SC meeting pages for the respective SARs.
joint 12/15/2017

To prepare document to analyze CIF Administrative Costs

Related Decision

Committee Meeting Completed June 2018 Part of the FY19 CIF Business Plan and Budget
CTF 06/16/2016

Revised document on CTF New Financing Modalities

Related Decision

Committee Meeting Completed December 2016 Proposal for CTF 2.0 has been presented at December 2016 Committee meeting
SREP 03/01/2019

To resubmit updated SREP IP for Zambia for endorsement including request for PPG approval

Related Decision

Approval by mail Completed May 2019 Revised Zambia Investment Plan approved on May 13, 2019
joint 12/15/2017

To Present Individual Risk Report - CTF, SREP, FIP and PPCR

Related Decision

Committee Meeting Completed June 2018 Risk report for CTF, FIP, PPCR, and SREP can be found on the respective TFC/SC meeting pages.
FIP 05/15/2015

Update in SAR: Include section on Gender

Related Decision

Committee Meeting Completed November 2015 Section was included in the SAR presented in the Nov2015 meeting
CTF 06/06/2017

To present a road map, including timelines of meetings and sequence of actions, together with outcomes of the technical analysis and due diligence, necessary to reach a decision on CTF 2.0

Related Decision

To be determined Completed June 2018 Technical work is completed
joint 11/09/2015

Report on progress made in operationalizing the ERM Dashboard

Related Decision

Notification by mail Completed January 2016 The Dashboard is operationalized.
joint 06/25/2014

Prepare paper outlining options for the commissioning of future national, thematic or program-level evaluations and/or a summative evaluation of the CIF

Related Decision

Committee Meeting Completed June 2016 The decision was materialized in the form of the E&L business plan
FIP 11/12/2015

Explore synergies between SCF programs in developing and implementing IPs ( if required)

Related Decision

Notification by mail Ongoing The request specifies that the guidelines should be provided 'if required'. So far, feedback from joint PPCR/FIP initial scoping missions indicate that there is no need for guidelines