DECISION TRACKER

The CIF Decision Tracker is an open access database that compiles all policy decisions taken by the CIF Trust Fund Committees and Sub-Committees during their semi-annual and intersessional meetings. It follows policy decisions through the entire decision-making process, from inception to enactment, to support more efficient work flow and greater transparency and accountability. Whenever possible, the tracker includes the resulting action taken to fulfill the demands of a decision (often a final report document). Users can sort the decisions through a variety of filters to tailor their search for information.

Program Meeting Date Task Reporting Methodology Status Exptected Completed Datesort icon Final Document Comments
CTF 03/01/2019

To Include in risk report: a) Detailed information on projects facing implementation risks in relation to the private sector portfolio;b) Information regarding fraud and sexual exploitation and abuse in CTF projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements;c) Report risk trends

Related Decision

Committee Meeting Completed June 2019 Included in the risk report of the CTF
FIP 03/01/2019

To include in FIP SAR: a) explore ways to enhance reporting on overall portfolio progress monitoring; b) explore ways to enhance reporting on overall portfolio progress monitoring; c) identify pathways to further support recipient countries in their investment plan implementation process

Related Decision

Committee Meeting Completed June 2019 Included in the FIP SAR
FIP 03/01/2019

To Include in risk report: a) details of the rationales for the implementation delays in projects flagged under implementation risk; b) details of actions taken to address the implementation delays in projects flagged for implementation risk as well as a workplan for ensuring that disbursements under these flagged projects will increase to a level where the projects will no longer be flagged for this risk; c) estimates of the dates by which disbursements will increase to levels such that these projects will no longer be flagged for implementation risk; d) Information regarding fraud and sexual exploitation and abuse in FIP projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements;e) Report risk trends

Related Decision

Committee Meeting Completed June 2019 Included in the risk report of the FIP
PPCR 03/01/2019

To Include in risk report: a) details of the rationales for the implementation delays in projects flagged under implementation risk; b) details of actions taken to address the implementation delays in projects flagged for implementation risk as well as a workplan for ensuring that disbursements under these flagged projects will increase to a level where the projects will no longer be flagged for this risk; c) estimates of the dates by which disbursements will increase to levels such that these projects will no longer be flagged for implementation risk; d) Information regarding fraud and sexual exploitation and abuse in FIP projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements; e) Report risk trends

Related Decision

Committee Meeting Completed June 2019 Include in the risk report of the PPCR
SREP 03/01/2019

To Include in risk report: a) details of the rationales for the implementation delays in projects flagged under implementation risk; b) details of actions taken to address the implementation delays in projects flagged for implementation risk as well as a workplan for ensuring that disbursements under these flagged projects will increase to a level where the projects will no longer be flagged for this risk; c) estimates of the dates by which disbursements will increase to levels such that these projects will no longer be flagged for implementation risk; d) Information regarding fraud and sexual exploitation and abuse in FIP projects implemented by such MDBs to the extent that such information is provided to their own MDB boards and subject to any necessary legal/confidentiality arrangements; e)Report risk trends

Related Decision

Committee Meeting Completed June 2019 Included in the risk report of the SREP
PPCR 03/01/2019

Prepare a brief options paper on how to utilize existing PPCR resources for a decision by the Sub-Committee

Related Decision

Approval by mail In progress June 2019
SREP 06/05/2019

To arrange a virtual discussion to discuss on options on how to improve the efficiency of SCF Trust Fund Committee and Sub-Committee meetings

Related Decision

Intersessional Meeting In progress December 2019
PPCR 06/05/2019

To arrange a virtual discussion to discuss on options on how to improve the efficiency of SCF Trust Fund Committee and Sub-Committee meetings

Related Decision

Intersessional Meeting In progress December 2019
PPCR 06/19/2019

To arrange a virtual discussion to discuss options for allocating available resources in the PPCR

Related Decision

Intersessional Meeting In progress December 2019
FIP 06/05/2019

To arrange a virtual discussion to discuss on options on how to improve the efficiency of SCF Trust Fund Committee and Sub-Committee meetings

Related Decision

Intersessional Meeting In progress December 2019
FIP 06/05/2019

To include in the FIP risk report: assessing, monitoring, and reporting credit risk exposures for each Strategic Climate Fund (SCF); and assessing, monitoring, and reporting interest rate risk exposures for all CIF programs.

Related Decision

Committee Meeting In progress January 2020 To include in the FIP risk report
PPCR 06/06/2019

To include in PPCR risk report: assessing, monitoring, and reporting credit risk exposures for each Strategic Climate Fund (SCF); and assessing, monitoring, and reporting interest rate risk exposures for all CIF programs.

Related Decision

Committee Meeting In progress January 2020 To include in the PPCR risk report
FIP 06/05/2019

Request to to develop the new program proposal on sustainable landscapes, in consultation with stakeholders

Related Decision

Committee Meeting In progress January 2020
SREP 06/05/2019

To prepare and submit an updated sealed pipeline taking into consideration cancellations to the Sub-Committee

Related Decision

Approval by mail In progress December 2020